Alblasserdam, 22 March, 2007 - Tuesday 22 March the contractors Idis Klusbedrijf and Bouwbedrijf Fortuyn started the construction of the NAVRO club house. After some preparations they began with placing prefab side panels. This went smoothly until the last panel of the front side when they discovered that the steel beam, on which the side panels are secured, was just a bit too long. The confusion was due to different versions of the building plans. The next day some centimetres of beam will be removed on the front and rear side beams with a welding torch. Furthermore more panels were placed on the rear side, except for the last one.