Alblasserdam, 3-4 April, 2007 - Due to circumstances the contractor couldn't work as much on the club house as planned. Nonetheless most of the floor was laid. The ventilation units and the pre-sawn parts of the bar are already delivered.

Wednesday evening 4 April we brought the heavy workbenches inside, because they are too big to be brought inside after the internal walls are erected. Since they were a few centimetres wide, we tilted them and brought them inside sideways. The biggest workbench however had drawers too close to it's legs. Without proper tools one set of drawers was removed and we finally got the workbench inside, but only just!

Previous    NAVRO club house construction 7    Next