Alblasserdam, 1 July, 2007 - This week again a lot of work was done. Thirsday 26 June Peter Heeren worked on the
ventilation. Wednesday evening 27 June some small jobs were done, like the decorative strips in the toilet, wooden backing
of the coat-hooks and cleaning the floor of the workshop. Harry Advokaat also continued working on the bar, which he also
did on Friday.
Sunday 1 July Peter Heeren almost finished his work on the ventilation and Peter Leemker also almost finished his electrical
work by connected all the lose ends to the distribution board.